LONGSHORE – ROCKHOUND 345 KV TRANSMISSION LINE PROJECT

For Oncor to continue to provide safe and reliable electric service in this area, a new transmission line is needed. Oncor is proposing to construct a new 345 kilovolt (kV) transmission line between Oncor’s existing Longshore Switch, located approximately 2.5 miles west of the intersection of United States Highway 87 and Farm-to-Market Road 461 in Howard County, Texas, and its existing Rockhound Switch, located approximately 2 miles southwest of the intersection of Interstate 20 and Farm-to-Market Road 829 in Midland County, Texas. The Proposed Transmission Line Project is currently planned for completion in summer 2030.

 

Voltage and Structure Type – The project includes a new 345 kV double-circuit transmission line constructed on self-supporting, monopole towers.

 

Public Meeting – Notice of the public meetings will be published in the following newspapers on the specified dates:



Newspaper

Publish Date

Midland Reporter-Telegram

Wednesday, June 15, 2026

Big Spring Herald

Wednesday, June 15, 2026

Stanton-Martin County Messenger

Thursday, June 16, 2026

Midland Reporter-Telegram

Wednesday, June 15, 2026

A public meeting will be held for this project. 

  • THURSDAY, JULY 30, 2026

    5:00 PM - 7:00 PM

     

    Martin County Community Complex    

    909 Millhollon Way,

    Stanton, TX, 79782


Public Participation Meeting materials handed out at the Public Meetings are available here. Public meeting materials reflect information that is accurate at the time of the meetings but could be updated in the filed Application.

Oncor will continue to accept landowner feedback by utilizing the Landowner Questionnaire. Please submit Questionnaires as soon as possible. A PDF copy of the Landowner Questionnaire is available here. Please submit via email to transmissionprojects@oncor.com

PROJECT MAPS

You can download a copy of the application’s filed Alternative Route Links and Land Use Constraints map to locate your property in the link below.

INTERACTIVE MAP

Explore the preliminary transmission route links using our interactive map. This tool allows you to view route links, nearby parcels and other project details in an easy-to-navigate format.

Estimated Project Timeline

 

Application Filing – Anticipated to be filed in February 2027.

 

PUC Decision – Anticipated by August 2027.

Oncor Representatives can be contacted regarding the Longshore to Rockhound 345 kV Transmission Line Project at 214.486.5370 or transmissionprojects@oncor.com