Oncor Electric Delivery Company LLC (Oncor) proposes to construct a new double-circuit 138 kilovolt (kV) transmission line within the cities of Arlington and Grand Prairie, Texas. The proposed transmission line will begin at Oncor’s proposed Division Substation, to be located southwest of Division Street and Stadium Drive. From that location, the proposed transmission line will extend east to an intermediate point along the existing Executive Parkway Switch–Sherry Switch transmission line located between the proposed Division Substation and State Highway (SH) 360. The proposed transmission line will then follow this existing transmission line corridor to the north of Division Street, before continuing eastward to a potential endpoint along the existing Liggett Switch–Cedar Hill Switch 138 kV transmission line, located east of SH 360. The exact locations of the intermediate point along the Executive Parkway Switch–Sherry Switch transmission line and of the eastern endpoint along the Liggett Switch–Cedar Hill Switch transmission line will be subject to selection and approval by the Public Utility Commission of Texas (PUCT).
Voltage and Structure Type – The project includes a new double-circuit 138 kV transmission line, constructed on steel monopole structures.
Public Meeting – Notice of the public meeting notice was published in the local newspaper during the week of 3/17/25. Public Meetings were held on Monday and Tuesday, March 24-25, 2025 at the Hilton Arlington at 2401 East Lamar Blvd. Arlington, Texas 76006 from 4:00 to 7:00PM. Click here for a copy of the public meeting material.
Constraints Maps – You can download the filed constraints maps below:
Application Filing – On August 7, 2025, Oncor filed an Application at the Public Utility Commission of Texas (PUCT) under Docket No. 58453 to construct and operate the proposed project. Click here for access to the docket on the PUCT Interchange.
PUC Decision – Notice of Approval was signed on January 26, 2026. Click here for a copy.
Oncor Representatives can be contacted regarding the Division 138 kV Transmission Line Project at 214.486.5216.