To continue to provide safe and reliable electric service in this area, Oncor Electric Delivery Company LLC (Oncor) is proposing to construct a double-circuit 345 kV transmission line between Oncor’s existing Mascho Switch and Oncor’s existing Lamesa Switch. The existing Mascho Switch (formerly known as Clearfork Switch) is located approximately 2.0 miles southwest of the intersection of State Highway (SH) 115 and Farm-to-Market (FM) Road 181 in Andrews County, Texas. The existing Lamesa Switch is located approximately 1.2 miles northwest of the intersection of SH 349 and
United States Highway 87 in Dawson County, Texas. The Proposed Transmission Line Project is currently planned for completion in Spring 2030.
Voltage and Structure Type – The project includes a new 345 kV Double Circuit Transmission Line, approximately 60 to 80 miles in length. The structure will be constructed on self-supporting, steel lattice tower structures.