To continue to provide safe and reliable electric service in this area, Oncor Electric Delivery Company LLC (Oncor) is proposing to construct a new double-circuit 345 kV transmission line in Culberson and Reeves Counties, with both circuits operational, between Oncor’s planned El Capitan Switch, located in Culberson County approximately 5.6 miles northwest of the intersection of Seven L Road and Rustler Springs Road, to Oncor’s proposed Dry Lake Switch, which will abut the south side of Farm-to-Market (FM) 2119, approximately 5.4 miles northwest of County Road (CR) 232 in Reeves County. The Proposed Transmission Line Project is currently planned for completion in Fall 2028.
Voltage and Structure Type – The project includes a new 345 kV Double Circuit Transmission Line, approximately 25 miles in length. The project will be constructed on self-supporting monopole structures.