BELL COUNTY EAST - BIG HILL 765 KV TRANSMISSION LINE PROJECT

For Oncor and LCRA TSC to continue to provide safe and reliable electric service in this area, a new 765 kV transmission line is needed. The Project would connect a new LCRA TSC 765 kV Big Hill Substation, located in close proximity to LCRA TSC’s existing Big Hill 345 kV Substation 13 miles northeast of the City of Eldorado in Schleicher County, Texas, and the expansion of Oncor’s existing Bell County East Switch, located 5.5 miles southeast of the City of Temple in Bell County, Texas. The Proposed Transmission Line Project is currently planned for completion in summer 2030.


Voltage and Structure Type

The project includes a new 765 kV single-circuit transmission line constructed on self-supporting, steel lattice towers.

 

 

Public Meeting

Notice of the public meetings was published in the following newspapers on the specified dates.

NewspaperPublish Date
Temple Daily TelegramTuesday, June 10, 2025
Burnet BulletinWednesday, June 11, 2025
Eden EchoThursday, June 12, 2025
Lampasas Dispatch RecordTuesday, June 10, 2025
Mason County NewsWednesday, June 11, 2025
Brady-Standard HeraldWednesday, June 11, 2025
Menard News and MessengerThursday, June 12, 2025
San Saba News & StarThursday, June 12, 2025
San Angelo Standard-TimesThursday, June 12, 2025
Georgetown-Williamson County SunWednesday, June 11, 2025

Three public participation meetings were held for the project.

  • Monday, June 16, 2025

    SALADO

    Salado ISD Meadows Room 601 N. Main Street Salado, Texas

    5:00 PM - 7:00 PM

  • Tuesday, June 17, 2025

    LAMPASAS

    Old Middle School Cafeteria 208 E. Avenue B Lampasas, Texas

    5:00 PM - 7:00 PM

  • Wednesday, June 18, 2025

    MENARD

    Menard County Community Center 303 Travis Street Menard, Texas

    5:00 PM - 7:00 PM

Public Participation Meeting materials handed out at the Public Meetings are available here.

PROJECT MAPS

You can download or view a copy of the preliminary routing, as presented at the public participation meetings below

Estimated Project Timeline

Application Filing – Anticipated in March 2026.

PUC Decision – Anticipated in September 2026.

Oncor Representatives can be contacted regarding the Bell County East – Big Hill 765 kV Transmission Line Project at 214.486.5216 or transmissionprojects@oncor.com.

LCRA TSC Representatives can be contacted at 512.578.1445 or BCBH@LCRA.org. Additional project details can also be found at www.lcra.org/BCBH.