Help
ESPAÑOL
click here to see search results
ENERGY SYSTEM DEVELOPERS Banner Image

ENERGY SYSTEM DEVELOPERS

INTERCONNECTION STEPS AND APPLICATIONS FOR LARGE DG SYSTEMS AND GRID RESOURCES

Developers of DER and grid resources, generally classified in sizes ranging from 500 kW up to 10 MW or more, can also begin the interconnection process by registering and submitting projects via the web-based project portal. We will review your request and contact you with details.

THE INTERCONNECTION PROCESS

Generally 9-12 Months for Most Large-Scale DG Projects. Time Frame Will Change Depending on the Size of a Project.

  • Apply

    • Contact Oncor for prescreen options and project classification
    • Prepare and submit application, technical drawings and sequence of operations
    • Participate in project kick off meeting with Oncor functional departments and EROT as required
  • Sign

    • Provide funding for the Tariff Pre-Interconnection Study and additional studies as required
    • Review engineering design and study results describing the required system upgrades and cost estimates
    • Secure appropriate agreements and fund project to proceed
  • Meter to Operate

    • Coordinate construction, commissioning, telemetry and relay testing as required to proceed to commercial operation
    • Finalize project requirement and begin commercial operation upon receiving written approval from Oncor

FREQUENTLY ASKED QUESTIONS 

Due to the complexity of interconnecting large-scale DG projects, an impact study must be performed and will be at the customer’s expense. Based on the results of the impact study, customer costs will be determined for system upgrades deemed necessary to complete the interconnection of the project.

Due to the complexity of interconnecting large-scale DG projects, an impact study must be performed. Customers should allow six to eight weeks for the completion of this study. Based on the results of the impact study, upgrades or changes may need to be made to the transmission or distribution equipment, and in some cases this equipment may have long lead times. In addition, some changes may require clearances that cannot be scheduled during high-load periods and could result in project delays. Oncor will work with customer schedules and provide expected construction scheduling timelines after funding and securing of proper documentation.

Upon request, Oncor will perform prescreens prior to an impact study. This simple screen will assess the requested generation capacity and determine if there is available distribution capacity at the requested location. Results of prescreens are subject to change and may vary from the findings of the final impact study.