Bell County East — TNP One 345 kV Transmission Project

transmission

As the state’s economy continues to grow at a brisk pace, it is important to take steps to ensure that a reliable electric system is in place to support electric load growth. Specifically, Oncor Electric Delivery proposes to construct an electric transmission line interconnecting the proposed Bell County East Switching Station, to be located southeast of Temple, with the existing TNP One Switching Station, located at the TNP One generating plant. As recommended by the Electric Reliability Council of Texas, this project is needed to ensure continued safe and reliable electric service to the state and the entire local region as new generation is added to support the State’s growing economy. Completion of the project will provide necessary system upgrades that will improve the transmission system’s ability to move bulk electric power north and south and will add valuable capacity to the entire transmission system. In addition, construction of this project will mitigate millions of dollars in congestion costs, resulting in savings in electricity production costs that will ultimately be passed on to electric consumers.

  • Voltage and Structure Type - The project is proposed to be a 345 kV transmission line constructed on Lattice Steel V Towers.

Project Details

  • Project One Pager - The One Pager includes a short description of the project, approval process and contact information.
  • Public Meeting - A Public Meeting Notice, which includes a map of the study area for the project was mailed to public officials and potentially affected landowners and published in the local newspapers. The Public Meeting was held in Rosebud on September 23, 2008.
  • Application – On May 22, 2009 Oncor filed an Application at the Public Utility Commission of Texas (PUCT) to construct and operate the proposed project. The Application includes a route map that shows the preferred and alternate routes included by Oncor. Oncor's Application was designated Docket No. 36995 at the PUCT. Oncor's Application and other documents filed at the PUCT in Docket No. 36995 can be viewed on the PUCT Website.
  • Public Notice – A Public Notice announcing the filing of Oncor's application in Docket No. 36995 was published in the local newspapers between May 27 and June 4, 2009. Cities, counties, and landowners potentially affected by the Application were mailed or hand delivered a notice of the filing of the application.
  • Procedural Schedule – Order No. 6 in Docket No. 36995 adopted a Procedural Schedule that sets out the dates for the administration of Oncor's application. Interested parties should be advised that the Procedural Schedule is potentially subject to change and should regularly consult the PUCT Website regarding any subsequent scheduling modifications.
  • Hearing on the Merits – A Hearing regarding Oncor’s Application is scheduled for February 22, 2010 at the State Office of Administrative Hearings in Austin.