Jacksboro — Willow Creek — Parker 345 kV Transmission Project
Texas is continuing to increase the integration of renewable energy into the Texas electric market. Reliable electric facilities must be in place to support the increased levels of renewable energy and to provide efficient means for this power to reach electric consumers. As part of this on-going process, Oncor is proposing a project that consists of rebuilding an existing single circuit electric transmission line into a double circuit transmission line. The project will connect the existing Jacksboro Switching Station to the existing Parker Switching Station, located just northwest of the city of Weatherford, utilizing the existing transmission line corridor. The Willow Creek Switching Station is a connecting station in this project that is located halfway between the Jacksboro and Parker stations. This project has been recommended by the Electric Reliability Council of Texas to ensure continued safe and reliable electric service to the State due to the increased integration of electric energy generated by wind production facilities. Completion of the project will provide necessary system upgrades that will improve the transmission system’s ability to efficiently move wind-generated electric power to market and will add valuable capacity to the entire transmission system.
- Voltage and Structure Type - The project is proposed to be a 345 kV transmission line constructed on Lattice Steel V Towers.
Project Details
- Project One Pager - The One Pager includes a short description of the project, approval process and contact information.
- Public Meeting - Public Meeting Notices were mailed to public officials and potentially affected landowners on January 23, 2009 and published in local newspapers beginning on January 23. The Public Meetings were held February 2, in Springtown and February 3 in Jacksboro. Informational handouts available at the meeting included an explanation of the projects, maps showing the routes, proposed structures and the licensing process.
- Application - On June 30, 2009, Oncor filed an Application at the Public Utility Commission of Texas (PUCT) under Docket No. 37119 to construct and operate the proposed project. The Application includes a route map that shows the preferred and alternate routes. Oncor's Application and other documents filed at the PUCT in Docket No. 37119 can be viewed on the PUCT Website.
- Public Notice - A Public Notice announcing the filing of Oncor's application in Docket No. 37119 was published in the local newspapers between July 9 and July 17, 2009. Cities, counties, and landowners potentially affected by the Application were mailed or hand delivered a notice of the filing of the application.
- Procedural Schedule - Order No. 5 in Docket No. 37119 adopted a Procedural Schedule that sets out the dates for the administration of Oncor's application. Interested parties should be advised that the Procedural Schedule is potentially subject to change and should regularly consult the PUCT Website regarding any subsequent scheduling modifications.
- Hearing on the Merits - A Hearing regarding Oncor’s Application is scheduled for October 8-9, 2009 at the State Office of Administrative Hearings in Austin.
Oncor representatives can be contacted regarding the Jacksboro — Willow Creek — Parker 345 kV Transmission Projects at 214-486-7333.